PRS Network Maintenance

Scheduled Maintenance Report for Philips HSDP

Completed

The scheduled maintenance has been completed.
Posted Feb 21, 2026 - 02:57 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 21, 2026 - 02:00 UTC

Scheduled

17-FEB-2026 23:45 (UTC): Maintenance activity on the Firewalls and Switches for AM3 (Amsterdam) Data Center. On February 21, 2026, from 02:00am – 06:00am (UTC), Philips Remote Services will be performing maintenance on the Firewalls and Switches for AM3 (Amsterdam) Data Center. The work involves patching of existing hardware. Impact to Users: Users will notice a temporary disruption as each device is upgraded. Minimal downtime is expected due to redundant systems.
Posted Feb 21, 2026 - 01:56 UTC
This scheduled maintenance affected: PRS (RSN Application Launch).